What Is a Risk Matrix?

A risk matrix is a simple grid that helps you prioritize hazards by combining two things: Likelihood (how often it can happen) and Severity (how bad it will be). The product (Risk = L × S) places each hazard into color-coded bands—think green (okay), amber/yellow (watch/mitigate), red (stop & fix).

Why Organizations Rely on Risk Matrices

Because they’re fast, visual, and scalable. From construction sites to oil & gas, and from hospitals to IT change control, a matrix standardizes risk decisions so teams act consistently.

Where 3×3 and 5×5 Fit in Risk Management

  • 3×3: small teams, repetitive tasks, quick toolbox talks, rapid approvals.
  • 5×5: larger operations, complex variations, need for finer differentiation and auditability.

For broader context on risk principles, see ISO 31000 (Risk management — Guidelines) here: ISO 31000 overview.


Core Concepts You Must Lock In

Likelihood, Severity, and Risk = L × S

  • Likelihood (L): probability or frequency band.
  • Severity (S): worst credible harm (injury, asset damage, environmental, reputation).
  • Risk Score: multiply L × S; interpret via bands (e.g., Low/Medium/High).

Ordinal Scales (And Why Not to Over-Quantify)

Both L and S are ordinal (ranked). Treat outputs as bands, not precise numbers. Use clear definitions and calibration sessions to avoid subjective drift.


3×3 Risk Matrix: Simple, Fast, Effective

Scale Definitions (Likelihood & Severity)

Likelihood
1 = Unlikely (heard of elsewhere, not here; < once in 5 years)
2 = Possible (could happen; once every 1–5 years)
3 = Likely (seen here; annually or more)

Severity
1 = Minor (first aid only; negligible downtime)
2 = Serious (medical treatment; lost-time injury; moderate damage)
3 = Major (fatality/life-altering; severe damage; major breach)

Color Bands and Action Thresholds

  • 1–2–3 = Low (Green) → Accept with routine controls
  • 4–6 = Medium (Yellow/Amber) → Mitigate before proceeding or add supervision
  • 7–9 = High (Red) → Stop work; escalate; redesign controls

Pros & Cons

Pros: lightning-fast, great for toolbox/shift briefings, minimal training.
Cons: coarse granularity; different risks may “tie,” making prioritization harder.


5×5 Risk Matrix: More Resolution, Finer Control

Scale Definitions (Likelihood & Severity)

Likelihood
1 = Rare (no known cases; < once in 10 years)
2 = Unlikely (heard of rarely; ~once in 5–10 years)
3 = Possible (could happen; every 1–5 years)
4 = Likely (seen in sector/site; yearly)
5 = Almost Certain (happens frequently; multiple times per year)

Severity
1 = Negligible (first aid; trivial cost)
2 = Minor (medical treatment; minor repairs)
3 = Moderate (LTI; significant repairs; reportable spill)
4 = Major (single fatality, permanent disability; major damage)
5 = Catastrophic (multi-fatality; complete asset loss; major environmental release)

Color Bands and Action Thresholds (Example)

  • 1–4 = Low (Green)
  • 5–9 = Moderate (Yellow)
  • 10–16 = High (Amber/Orange)
  • 17–25 = Extreme (Red)

(Tune thresholds to your risk appetite and legal framework.)

Pros & Cons

Pros: better discrimination, stronger audit trail, clearer escalation.
Cons: more training, risk of false precision if scales aren’t well defined.


Comparing 3×3 vs 5×5: Which One Should You Choose?

Decision Criteria (Team Maturity, Risk Appetite, Industry)

  • Scope & Variety of Tasks: Complex/high-hazard → 5×5. Routine/low-variance → 3×3.
  • Competency & Training: New teams → 3×3 (start simple), mature teams → 5×5.
  • Regulatory & Client Demands: Some sectors expect 5×5 detail.
  • Throughput Needs: If approvals must be very fast, 3×3 may win.

Mapping 5×5 Back to 3×3 (and Vice Versa)

  • 5×5 → 3×3 (compression):
    • Likelihood (1–2 → 1), (3 → 2), (4–5 → 3)
    • Severity (1–2 → 1), (3 → 2), (4–5 → 3)
  • 3×3 → 5×5 (expansion):
    • Likelihood 1→(1–2), 2→(3), 3→(4–5)
    • Severity 1→(1–2), 2→(3), 3→(4–5)

This mapping keeps risk categories broadly consistent across tools.


Designing Your Matrix Step-by-Step

Define Clear, Behavior-Anchored Scales

Avoid vague labels like “may happen.” Anchor each level with time-bound frequency (e.g., “seen here annually”) and consequence descriptors (e.g., “LTI, reportable spill”). Include people, asset, environment, reputation in severity notes if relevant.

Set Categories, Colors, and Decision Rules

  • Decide bands (e.g., Low/Moderate/High/Extreme).
  • Assign colors that are color-blind friendly (use patterns or labels too).
  • Define what to do per band: permit requirements, sign-offs, PPE upgrades, isolation needs, stop-work triggers.

Build the Register and Workflows

Link your matrix to a risk register with fields like: Hazard, Scenario, L (pre), S (pre), Score (pre), Controls, L (post), S (post), Residual Score, Owner, Due Date, Status.


Worked Example #1 (3×3): Hot-Work in a Maintenance Bay

Scenario: Cutting brackets with an angle grinder near stored lubricants; typical daily activity.

Pre-Control Scoring (3×3):

  • Likelihood (L): 3 = Likely (this task occurs frequently; sparks common)
  • Severity (S): 3 = Major (credible fire/explosion; severe injury)
  • Risk Score: 3 × 3 = 9 → High (Red)

Controls Planned:

  • Hot-work permit, remove combustibles to 15 m or shield, fire watch, Class ABC extinguisher ready, gas test if in confined area, stop fans that spread sparks, non-sparking screens, full PPE (FR coveralls, gloves, visor), housekeeping & post-work fire watch (30–60 min).

Residual Risk (3×3):

  • Likelihood: 2 = Possible (with screens, housekeeping, permit, fire watch)
  • Severity: 2 = Serious (consequences reduced by separation & readiness)
  • Residual Score: 2 × 2 = 4 → Medium (Amber)

Decision: Proceed with permit, supervisor sign-off, and strict fire watch.


Worked Example #2 (5×5): Working at Height on a Scaffold

Scenario: Installing pipe racks at 8 m height, busy deck below.

Pre-Control Scoring (5×5):

  • Likelihood (L): 4 = Likely (activity repeated daily; multiple crew)
  • Severity (S): 4 = Major (fall can be fatal; heavy objects overhead)
  • Risk Score: 4 × 4 = 16 → High (Amber/Orange)

Controls Planned:

  • Certified scaffold with green tag, mid-rails/toe-boards, double lanyard 100% tie-off with shock absorber, anchor points rated, exclusion zone below, tool lanyards, pre-use inspection, trained erectors, weather/wind checks, rescue plan with practiced drill, supervisor oversight.

Residual Risk (5×5):

  • Likelihood: 2 = Unlikely (controls significantly lower exposure)
  • Severity: 4 = Major (severity remains high if a fall occurs)
  • Residual Score: 2 × 4 = 8 → Moderate (Yellow)

Decision: Proceed with permit to work, continue monitoring wind, enforce 100% tie-off and exclusion zone.


Risk Categories, Triggers, and ALARP

What “Acceptable,” “Tolerable,” and “Unacceptable” Mean

  • Acceptable: Residual risk within green; handle via routine procedures.
  • Tolerable: Yellow/Amber; reduce further if reasonably practicable (cost–benefit).
  • Unacceptable: Red; do not proceed until risk is reduced.

Documenting “So Far As Is Reasonably Practicable”

Record alternatives considered, cost/effort, and why chosen controls are proportionate. This is essential for ALARP defensibility and regulatory audits.


Implementation Tips (Excel/Sheets, Tooling, Training)

Conditional Formatting & Data Validation

  • Build dropdowns for L and S using your definitions.
  • Compute =L*S for score; color cells by band thresholds.
  • Lock definitions on a separate tab; link to all sheets to ensure consistency.

Version Control, Audit Trails, and Change Logs

  • Stamp each matrix with a version and effective date.
  • Keep an audit log for changes in scales or thresholds.
  • Train users; run calibration workshops quarterly.

Common Pitfalls and How to Avoid Them

False Precision & Score Gaming

Avoid implying that 12 is “twice” as risky as 6. These are bands, not physics. Limit incentives to “game” scores (e.g., don’t set a hard approval cutoff that pushes people to under-score).

Ignoring Rare-But-Severe Events

Catastrophic but rare scenarios (e.g., confined-space asphyxiation) deserve special attention, even if multiplied scores seem moderate. Use bow-tie analysis or specific critical control verification.


When to Upgrade/Downgrade Your Matrix

From 3×3 → 5×5 for Complex Operations

Signals: frequent “ties,” many amber decisions needing finer resolution, client/regulator asks for more granularity.

From 5×5 → 3×3 to Speed Decisions

Signals: analysis paralysis, low adoption on the shop floor, excessive time per permit. Keep a 5×5 for engineering studies, but use 3×3 for frontline permits.


Calibration Workshops: Keeping Scores Consistent

Facilitated Scoring Sessions

Bring cross-functional teams. Score real jobs together. Discuss why a scenario is “Possible” vs “Likely.” Capture examples and codify them in the definitions.

Back-Testing Against Incidents

Review past incidents: Would your current matrix have flagged them as high enough? If not, tune definitions/thresholds and train again.


Template: Ready-to-Use Scale Definitions

3×3 Likelihood Definitions

LTitlePractical Anchor
1UnlikelyNot seen here; < once in 5 years
2PossibleCould happen; once every 1–5 years
3LikelySeen here; at least annually

3×3 Severity Definitions

STitlePractical Anchor
1MinorFirst aid; < 1 day downtime; small clean-up
2SeriousMedical treatment or LTI; moderate repair cost; reportable near miss
3MajorSingle fatality/permanent disability; major asset damage; significant release

3×3 Bands (example):
1–3 Low, 4–6 Medium, 7–9 High.


5×5 Likelihood Definitions

LTitlePractical Anchor
1RareNo known cases; < once in 10 years
2UnlikelyVery infrequent; once in 5–10 years
3PossibleCould occur; every 1–5 years
4LikelyOccurs in sector/site; annually
5Almost CertainHappens frequently; multiple times per year

5×5 Severity Definitions

STitlePractical Anchor
1NegligibleFirst aid only; trivial cost
2MinorMedical treatment; minor repair
3ModerateLTI; significant repair; moderate environmental effect
4MajorSingle fatality, life-altering injury; major asset damage; major environmental harm
5CatastrophicMultiple fatalities; complete asset loss; severe environmental disaster

5×5 Bands (example):
1–4 Low, 5–9 Moderate, 10–16 High, 17–25 Extreme.


Conclusion & Next Steps

Designing a 3×3 vs 5×5 risk matrix is about fit: the mix of your hazards, team maturity, and the speed vs precision you need. Start with clear, behavior-anchored definitions, decide thresholds and actions, and integrate them into your permits, audits, and training. Use 3×3 when you need speed and simplicity; choose 5×5 when your environment demands finer discrimination and stronger auditability. Keep calibrating with workshops, back-testing against incidents, and refining ALARP justifications. The result? Decisions that are faster, clearer, and defensible—every single shift.

Gas Cylinder Handling JSA – Job Safety Analysis

Tower Crane Operation JSA – Job Safety Analysis

Forklift Operation JSA – Job Safety Analysis

Lockout/Tagout LOTO Procedures JSA – Job Safety Analysis

Site Housekeeping Activities JSA – Job Safety Analysis


FAQs

1) Is multiplying L × S statistically valid?
It’s a pragmatic heuristic on ordinal scales. Treat scores as bands for decisions, not exact math. Use additional analysis (e.g., bow-tie) for critical hazards.

2) How do I pick thresholds for color bands?
Start with common ranges (e.g., 5×5: 1–4, 5–9, 10–16, 17–25) and adjust after calibration workshops and incident back-testing to match your risk appetite.

3) Can I use different scales for environment vs people?
Yes. Many organizations assess People, Environment, Asset, Reputation separately and then take the worst case or apply weighted rules.

4) When should I switch from 3×3 to 5×5?
If you’re seeing frequent “ties,” complex jobs, or heavier regulatory/client oversight, upgrade to 5×5 for granularity and audit strength.

5) How do I ensure consistency across shifts and sites?
Provide behavior-anchored definitions, run regular calibration sessions, audit the risk register, and maintain a version-controlled matrix.